Installing structured packing (packing) is critical for maintaining the long-term stability and efficiency of tower internal systems in chemical processing. Follow these professional steps to ensure a secure, aligned, and leak-free installation:
1. Pre-Installation Preparation
First, gather all necessary tools (e.g., level, measuring tape, lifting equipment) and materials (packing sheets, support grids, sealing compound). Verify the packing specifications match the tower dimensions and process requirements. Ensure the tower interior is clean, free of debris, and structurally sound—check for cracks or uneven surfaces that could compromise stability.
/1 (43).jpg)
2. Install Support Grids
Start by placing the support grid (a foundational component) at the designated height. Use alignment pins to ensure it sits perfectly horizontal; any tilt can cause uneven packing pressure and premature wear. Secure the grid to the tower walls using anti-vibration fasteners to prevent movement during operation.
3. Load Packing Sheets with Precision
/1 (104).jpg)
Carefully unroll or lift packing sheets, aligning their corrugations with the tower axis. Overlap adjacent sheets by 5–10 mm to avoid gaps, which can reduce separation efficiency. Use a level to ensure each layer is flat and evenly spaced. For large towers, use a grid or guide rails to maintain alignment as you stack layers—misalignment of even 1° can lead to channeling and instability.
4. Secure Edges and Seals
At the top and bottom of the packing bed, install edge protectors to prevent sheet damage. Apply a bead of high-temperature, chemical-resistant sealing compound around the packing perimeter to seal gaps between the packing and tower walls. For vertical towers, use a compression seal or O-ring to ensure a tight fit, minimizing fluid bypass.
5. Post-Installation Inspection
/金属规整0712 (2).png)
After loading, perform a final check: verify all layers are level, support grids are secure, and seals are intact. Use a borescope or camera to inspect internal gaps or misalignments. Conduct a gentle fluid flow test (if possible) to ensure uniform distribution—uneven flow indicates installation issues that could lead to stability problems over time.
By following these steps, you’ll establish a structured packing system that delivers consistent performance, reduces maintenance needs, and extends the lifespan of your tower internal. Proper installation is the foundation for long-term stability in chemical distillation, absorption, and other separation processes.